Verified November 17, 2026 against Toronto Zoning By-law 569-2013 (Chapter 150.7) and City of Toronto building and planning pages. By Local Toronto Editorial.
Short answer: Yes, most Toronto homeowners in a residential zone can build a garden suite in the backyard without a rezoning, as long as it meets the zoning rules and the fire access rules and gets a building permit. Since the 2025 update (By-law 849-2025), a garden suite can be up to 6.3 metres tall and two storeys if it sits at least 7.5 metres from the house, or up to 4.0 metres tall if it is closer, with at least 4.0 metres of separation. A one-storey suite is capped at 60 m² of gross floor area and a two-storey suite at 120 m², and it must be smaller than the house. No parking space is needed, and firefighters need a clear path at least 1.0 metre wide from the street, normally no longer than 45 metres.
What counts as a garden suite
The City defines a garden suite as a self-contained home inside an ancillary building, usually in the rear yard, that is separate from the main house and does not sit on a public lane. It has its own kitchen and bathroom. If your lot backs onto a public laneway, the building is a laneway suite instead, and different rules apply.
Toronto first allowed garden suites city-wide when Council adopted the Official Plan and zoning amendments on February 2, 2022 (Zoning By-law 101-2022). After a monitoring program and a new provincial regulation, O. Reg. 462/24, Council approved a second round of changes in 2025. The zoning amendment is By-law 849-2025, and the City says it is in force except for one appeal on a single property. Most of the rules below come from Chapter 150.7 of Zoning By-law 569-2013 as it reads now.
Which properties qualify
- Zoning: garden suites are permitted in the five residential zones of Zoning By-law 569-2013: R, RD, RS, RT and RM. Check your zone on the City’s Zoning By-law Interactive Map.
- Older zoning by-laws: By-law 101-2022 does not apply to land still zoned under a former municipal by-law (for example the old Etobicoke or North York codes). If that is your situation, the City asks you to call Toronto Building at 416-397-5330.
- One per lot: a lot can have one ancillary building with either a garden suite or a laneway suite, not both. The garden suite holds one unit.
- Combined with other units: Toronto has allowed up to four units in a house since its 2023 multiplex changes, plus a garden or laneway suite, which is how the City’s monitoring report arrives at five units on most lots.
- No severance: the City says you cannot split the lot so the house and garden suite end up on separate lots.
Trees can also decide the project. The City’s position is that a garden suite should not remove a healthy by-law protected tree, which on private land means a tree 30 cm in diameter or more, and any tree on City land. Our tree removal permit guide explains the permit side.
Size, height and setback rules
These are the main standards in Chapter 150.7 after the 2025 amendments. Height is measured from average grade around the building.
| Rule | What the by-law says |
|---|---|
| Maximum height | 4.0 m if the suite is less than 7.5 m from the house; 6.3 m if it is 7.5 m or more away. Two storeys maximum. |
| Separation from the house | At least 4.0 m if the suite is 4.0 m tall or less; at least 7.5 m if taller. In part of the east end (roughly Coxwell to Victoria Park, south of the Don River and Sunrise Avenue to the lake), a taller suite needs 5.0 m. |
| Rear yard setback | 1.5 m. On lots deeper than 45 m, the greater of 1.5 m or half the suite’s height. Add 1.5 m if the rear wall has windows or other openings above 4.0 m and the lot behind is residential. |
| Side yard setback, with side windows or doors | The greater of 1.5 m or 10% of the lot frontage, with the 10% amount capped at 3.0 m. |
| Side yard setback, no side openings | The greater of 0.6 m or 10% of the lot frontage, capped at 3.0 m. |
| Corner lots | Where the house on the next lot faces the flanking street, the side setback is the average of that house’s front setback and your house’s required side setback, never less than 1.5 m. |
| Gross floor area | Maximum 60 m² for a one-storey suite and 120 m² for a two-storey suite, and always less than the gross floor area of the house. |
| Lot coverage | Either all buildings together cover no more than 45% of the lot, or the suite is left out of the main calculation and all ancillary buildings together cover no more than 20% of the lot. |
| Soft landscaping | At least 50% of the rear yard area must be soft landscaping on lots wider than 6.0 m, or 25% on lots 6.0 m wide or less. |
| Parking | No parking space required for the suite or for the units in the house. Two bicycle parking spaces are required. |
| Decks and platforms | Smaller than 10% of the suite’s interior floor area, on the first floor only, no more than 0.2 m above the floor, with a 1.5 m opaque screen on sides facing a side yard. |
A few points that surprise owners:
- Basements are allowed. The 2025 change switched the size test to gross floor area, and the monitoring report explains that the same deductions used for houses, including basement space, now apply to the suite.
- Setbacks apply below ground too. The required setbacks cover every part of the suite above and below ground, except footings.
- The angular planes are gone. Older City summaries from February 2022 describe 45 degree angular planes. The monitoring report recommended deleting them to match O. Reg. 462/24, and they are not in the current Chapter 150.7 text. Ignore any guide that still treats them as a rule.
- Converting a garage: an existing garage or shed built with a permit keeps its existing setbacks and separation, but still has to meet the height, floor area and landscaping rules. If it was built without a permit, the City treats it as a new building.
If a design misses one of these numbers, the owner can apply for a minor variance at the Committee of Adjustment. Between 2022 and August 2024 there were 233 garden suite variance applications, and the City’s consultant found an 80% approval rate, with side and rear setbacks, soft landscaping and height among the most common requests. Neighbours worried about a two-storey suite next door may find our guide to what your neighbour is allowed to build useful.

Fire access: the rule that stops many projects
Fire access is not a zoning rule. It comes from the Ontario Building Code and is checked by Toronto Building and Toronto Fire Services, and the City says it cannot be changed through a minor variance. A garden suite has only one way in for firefighters, through your property beside the house, so this is often the first thing to check.
| Requirement | Standard |
|---|---|
| Path width and height (no sprinklers) | At least 1.0 m wide and 2.1 m high |
| Path width and height (sprinklered suite) | At least 0.9 m wide and 2.1 m high |
| Path length | No more than 45 m from the public street to the suite’s entrance |
| Longer path | Up to 90 m with one of the City’s two extra fire safety options |
| Fire hydrant | Within 45 m of where a fire truck would park in front of the property |
Gas and hydro meters are allowed to stick into the path. Air conditioners, fences and stored items are a different matter, so measure the side yard before paying for drawings.
The two options for a path up to 90 metres are:
- Option 1: an automatic sprinkler system designed by a professional engineer, an exterior strobe light on the main house that can be seen from the street, and an engineered smoke alarm and warning system.
- Option 2: no sprinklers, but upgraded fire protection on the exterior walls (fewer openings, fire-rated walls and non-combustible cladding where the suite is close to a lot line), plus the same strobe light and warning system.
If your side yard is too narrow, the path can be shared with the neighbour’s side yard through a Limiting Distance Agreement with the City, registered on both titles. The City provides a template, both owners usually need lawyers, and the City charges its legal time at $274.65 an hour. The agreement only gives access to firefighters, not to tenants.
Garden suite rules checker
Enter your lot and design details to see which zoning numbers apply. This covers interior lots only and is a quick screen, not a zoning review.
Based on Chapter 150.7 of By-law 569-2013 as amended by By-law 849-2025. The permit fee line uses the 2026 rate of $18.56 per m² as a rough guide; Toronto Building sets the actual fee. Does not check fire access, trees, lot coverage, landscaping or site-specific exceptions.
With the example inputs (a 7.6 m by 36 m lot, a two-storey 90 m² suite set 8 m behind the house with side windows), the side setback is 1.5 m because 10% of the frontage is only 0.76 m, and the rear setback is 1.5 m. Adding upper rear windows would push the rear setback to 3.0 m.
Permits, pre-approved plans and fees
Every garden suite needs a building permit. The City recommends getting a Zoning Applicable Law Certificate first so the permit application is complete and any variance is spotted early. If a variance is needed, it has to be approved before the permit is issued.
Made in Toronto pre-approved plans
Toronto Building offers four free pre-approved designs: a studio garden suite, a two-bedroom garden suite, and studio and two-bedroom laneway suites. Each comes with a heat pump or forced air version and three fire access versions (standard 45 m access, Option 1 and Option 2). The drawings were last updated on August 17, 2026.
- You still apply for a permit, but you quote the plan number instead of uploading the drawings.
- You still submit a site plan and a lot grading plan, because placement on your lot is reviewed for zoning and Building Code compliance.
- Any change to the plan, including HVAC or plumbing changes, means it is no longer pre-approved.
- The owner or designer using the plan takes responsibility for the design.
Other forms in the package include the permit application, the designer information schedule, a municipal road damage deposit, the residential infill public notice declaration, a tree declaration form and an overhead electrical conductors declaration.
Permit fee
For new single-family residential construction, Toronto's 2026 permit fee is $18.56 per m². On that rate, a 60 m² suite works out to about $1,113.60 and a 120 m² suite to about $2,227.20. These are estimates; the City calculates the actual fee, and mechanical, plumbing and drain permits can be applied for separately.
Utilities are expected to run from the main house. The City notes that running new pipes through or under another unit can trigger Building Code requirements in the main house, so involve your designer and plumber early.
Development charges and other costs
| Cost item | How it applies to a garden suite |
|---|---|
| Development charges | Exempt when the suite is the second, third or fourth unit on the lot (Municipal Code 415-6(A)(2)). |
| DC deferral | Where a charge would apply, the City's deferral program can defer it for 20 years. It becomes payable if a new lot or condominium is created, or if the property is sold without an assumption agreement. A Section 118 restriction is registered on title. |
| Parkland dedication | Exempt for one ancillary unit, up to five units in total on the lot. |
| Affordable Laneway Suites Program (forgivable loan) | Discontinued. The City says it is not expected to return. |
Construction is the big number. The City's monitoring report says building permit data showed an average estimated construction cost of about $260,000 and a median of about $180,000, but warned these figures may be underreported, and that industry experts put real costs at $300,000 to $400,000 or more depending on servicing. Treat any quote below that range with care, and budget for surveys, drawings, an arborist if trees are near, and utility connections.
A garden suite is also new living space that adds to the property's value for tax purposes. Our GTA property tax rates guide shows Toronto's 2026 rate.

Renting it out and other uses
- Long-term rental: the zoning does not regulate tenure, so a garden suite can be rented or used by family. A rental is covered by Ontario's Residential Tenancies Act. Units first occupied after November 15, 2018 are exempt from the yearly rent increase guideline, though other rules still apply; see our 2027 rent increase guideline guide.
- Short-term rental: only allowed if the garden suite itself is someone's principal residence, the same test that applies elsewhere in Toronto. Our Airbnb rules guide covers registration.
- Home business: permitted only if the suite is separately occupied as a principal residence, under the City's home occupation rules.
- Basement apartment too: a house can have a secondary suite and a garden suite on the same lot. Our guide to renting out a basement in Toronto covers the suite inside the house.
This guide summarizes published City rules and is not legal or tax advice. Site-specific zoning exceptions can change what applies to your lot, so confirm with a zoning review before you build.
Buying a house with a garden suite
Permit data shows interest growing fast: 56 garden suite permit applications in 2022, 361 in 2024, and 812 in total by May 8, 2025, with 480 permits issued. More resale homes will come with one. Before you firm up an offer, check:
- Permit history: ask for the building permit and confirm it was closed after final inspection. A suite built without a permit can be treated as a new building. Our guide to buying a home with unpermitted renovations explains records requests and fixes.
- Title registrations: look for a DC deferral agreement and Section 118 restriction, or a Limiting Distance Agreement for fire access. Your lawyer should explain both before closing.
- Tenancy: if the suite is rented, the tenant's lease continues after the sale.
- Services: find out how water, sewer, power and heat are shared with the house and whether the suite has separate meters.
Thinking of buying a lot with room for a garden suite, or selling a home that has one? Our team can help you find a home or arrange a free home evaluation. Building outside Toronto? See our Mississauga garden suite guide and Brampton garden suite guide, or browse the Toronto real estate hub.
FAQ
Do I need a permit to build a garden suite in Toronto?
Yes. Every garden suite needs a building permit, and it must meet the zoning by-law, the Ontario Building Code, fire access requirements and tree rules. If the design does not meet a zoning standard, a minor variance from the Committee of Adjustment is needed before the permit is issued.
How big can a garden suite be in Toronto?
A one-storey garden suite can have up to 60 m² of gross floor area and a two-storey suite up to 120 m², and the suite must always be smaller than the house on the lot. Height is limited to 4.0 m if the suite is less than 7.5 m from the house, or 6.3 m if it is 7.5 m or more away.
How far does a garden suite have to be from the house?
At least 4.0 m for a suite 4.0 m tall or less, and at least 7.5 m for a taller suite. In part of the east end between Coxwell and Victoria Park, a taller suite needs 5.0 m.
Does a Toronto garden suite need a parking space?
No. Zoning By-law 569-2013 requires no parking space for a garden suite or for the units in the house on the same lot. It does require two bicycle parking spaces.
What is the fire access rule for garden suites?
Firefighters need a clear path at least 1.0 m wide and 2.1 m high (0.9 m if the suite is sprinklered), no more than 45 m from the street to the suite's door. The path can be up to 90 m with extra fire safety measures, and a hydrant must be within 45 m of where the truck would park. This rule cannot be changed by a minor variance.
Do I pay development charges on a garden suite?
Usually not. Toronto exempts a garden suite from development charges when it is the second, third or fourth unit on the lot. Where a charge would apply, the City offers a 20-year deferral, which becomes payable if the lot is severed or the property is sold without an assumption agreement.
Sources
- City of Toronto, Zoning By-law 569-2013 (office consolidation, city-wide amendments to April 30, 2026), Chapter 150.7 Garden Suites, as amended by By-laws 101-2022, 420-2023, 648-2025 and 849-2025.
- City of Toronto, Garden Suites, City Planning (modified August 21, 2026).
- City of Toronto, Expanding Housing Options in Neighbourhoods: Garden Suites Monitoring Program, Final Report (June 27, 2025, Item 2025.PH23.1).
- City of Toronto, Pre-Approved Garden and Laneway Suite Building Plans (modified October 30, 2026).
- City of Toronto, Providing Fire Department Access to a New Garden Suite (modified September 29, 2026).
- City of Toronto, Laneway and Garden Suite Development Charges Deferral Program (modified August 14, 2026).
- Province of Ontario, O. Reg. 462/24 (Additional Residential Units), in force November 20, 2024.
- Province of Ontario, Residential rent increases (rent increase guideline exemptions).
Images: AI-generated illustrations created for this guide. They do not show real properties.
Local Toronto, HomeLife Landmark Realty Inc., Brokerage.